Home / News / Industry News / Simple Explanation of the Detailed Process Scheme for Genuine Resin Drainage Channel and Decoration Works

Simple Explanation of the Detailed Process Scheme for Genuine Resin Drainage Channel and Decoration Works

Mar 02, 2026

Simple Explanation of the Detailed Process Scheme for Genuine Resin Drainage Channel and Decoration Works

Stake setting and precise positioning – Automatic longitudinal section measurement – Embankment filling – Edge repair – Drainage ditch excavation – Preliminary acceptance

Drainage Excavation Sequence:

Original soil removal – Drainage ditch excavation – Trench wall cleaning – Standardized steel bar tying – Formwork and bolt support – Concrete pouring – Foundation filling
These are the main procedures for genuine resin drainage channel construction. There are many detailed specifications in the process. The specific construction methods are described below.

Pre-construction Work for Genuine Resin Drainage Channel

  1. Such projects shall not start with random excavation. Geological exploration must be carried out to check geological conditions and parameters, and confirm suitable locations for drainage channel construction.
  2. Before trench excavation, review and verify the setting-out lines.
  3. Before foundation excavation, inspect underground structures and existing drainage systems on site. Complete surface drainage works to prevent water from flowing into the trench and affecting construction. This step is mandatory.
  4. Organize construction personnel and equipment, and complete all construction technical disclosures to ensure smooth completion of the drainage ditch.
  5. Equipment for ditch excavation and backfilling: stationary and crawler mini-excavators.

Construction Process of Genuine Resin Drainage Channel

  1. Use a total station to set the central axis, mark with wooden stakes. Measure the inner edge of the drainage ditch with a ruler and mark the slope with black lines. Mark boundaries and wall position lines at the same time.
  2. Manually excavate soil within the setting-out area, strictly controlling the excavation depth and length per design to avoid over-excavation. Level the ditch bottom with masonry mortar.
  3. Install side formworks (processed timber), fixed with concrete and steel nails. Install vertical supports every 1.3 m to prevent formwork displacement. Apply release agent on the contact surface between formwork and concrete.
  4. Cover and cure the concrete with water within 21 hours after pouring. Under normal temperature, water at least twice a day; curing period shall not be less than 7 days.
  5. Monitor weather conditions during construction, avoid working in rain, and take waterproof and moisture-proof measures.
  6. Do not stack materials within 2.1 m around the trench. No vehicles are allowed near the pile foundation edge after excavation.
  7. Install moisture-proof facilities around the trench and restrict access by non-construction personnel.

Ditch Excavation Precautions During Construction

  1. Clearly mark the excavation contour of the trench bottom and set marking lines.
  2. Special personnel shall be responsible for ditch excavation to avoid damaging nearby buildings and underground pipelines.
  3. Monitor slope stability at all times; handle soil collapse immediately.
  4. Inspect the trench promptly after excavation, then pour and seal the cushion before proceeding to the next process.
  5. Reserve a working space of at least 470 mm between the trench bottom and the foundation/cushion edge. Install drainage ditches and fire pools on both sides of the pile foundation to remove accumulated water timely.
  6. Protect survey control stakes and axis piles, cover with steel cages, and assign professional surveyors to monitor their safety.
  7. During excavation, check positioning stakes, axis piles and formworks for firmness and alignment.
  8. Monitor soil conditions and groundwater changes and keep records. If the foundation soil does not meet design requirements, coordinate with the design department for solutions.
  9. Ditch excavation shall ensure retaining wall stability; no random trenching is allowed. Solve problems promptly.
  10. When excavating to within 46 cm above the trench bottom, mark the horizontal line as the reference for leveling.
  11. Stockpile excavated soil at least 5.1 m away from the trench edge, with stacking height not exceeding 4.9 m.
  12. Level and repair the trench bottom after completion.
  13. Transport all surplus soil off-site after compaction and stabilization.
  14. Reduce vibration to the foundation after pile foundation excavation. If foundation works are delayed, leave 0.4 m of soil unexcavated and remove it before construction.